The Redmond Pool is currently in the first phase of essential improvements. Recently contractors discovered an existing but unknown condition. The substructure of the pool is compromised; there are areas where concrete has deteriorated leaving aggregate and rusting rebar behind. The damage extends sporadically from approximately 1’ to 5’ off the bottom of the pool’s deep end. This unexpected repair will take approximately 3 months to correct the substructure and complete the pool lining. To accommodate this unexpected delay the Redmond Pool will not open in November as previously scheduled and will remain closed to complete both Phase 1 and 2 and is expected to re-open in fall of 2020.