- Home
- Government
- Departments & Divisions
- Planning
- Projects
- Pressure Reducing Valve (PRV) Station Replacement
The City uses approximately 84 pressure reducing valve (PRV) stations to manage water pressure in the City’s distribution system. Many of these PRV stations were built in the 1960s and 1970s and are in need of refurbishment. City staff inspected and evaluated all of Redmond’s PRV stations and generated a list of 27 stations needing rehabilitation or replacement. These stations no longer meet City standards due to pipe corrosion, age, type of materials used, and environmental conditions. Corrosion is the main cause of degradation, but other issues include vault drainage and safe access.
PRV Station replacement will occur in phases. Typical work at each location includes installing a new vault, valves, and piping and restoring all street, sidewalk and landscape within the limits of construction. Most stations are replaced in the same location, but due to construction and maintenance access difficulties, some stations may be relocated.
Phase 2 of this project will abandon and replace seven PRV stations throughout Redmond as shown in the Phase 2 Map.
The current construction schedule is below:
Site | Approximate Start Month/Status |
---|---|
Preparation work for all seven sites | October 2022 |
PRV 21 - 10706 181st Ave NE | Substantially Complete |
PRV 56 - 132nd Ave NE and NE 93rd St | Substantially Complete |
PRV 39 - 7001 NE Old Redmond Road | August-October 2023 |
PRV 40 - 7575 NE Old Redmond Road | Substantially Complete |
PRV 41 - 7939 152nd Ave NE/Redmond Way | September-October 2023 |
PRV 42 - 8255 149th Way NE | October-November 2023 |
PRV 49 - 139th Ave NE and Redmond Way and 140th Ave NE and Redmond Way (this station is being relocated) | Substantially Complete |
Phase 1 of this project, completed in November 2019, abandoned and replaced 10 PRV stations throughout Redmond.
Location:
Various locations throughout the City
Project Phase:
Construction
Timeline:
Construction began in October 2022 with completion of all stations expected in November 2023.
State Environmental Policy Act
SEPA-2021-00278