Avondale Road Pavement Management

Aerial viewe of Avondale Road Pavement project area

Project Overview

This project rehabilitated Avondale Road, including ADA curb ramp and pedestrian signal upgrades. Work included grind and overlay of the roadway surface and rechannelization to include bike lanes. The project:

  • Overlayed new asphalt to improve the driving surface 
  • Increased the width of the bike lane to improve cyclist safety 
  • Narrowed the vehicle lanes of Avondale from 12 feet to 10.5 feet 
  • Added all new striping of vehicle and bike lanes

Construction Details

What you can expect:

  • Estimated construction timeline: August – October 2023 
  • Work hours: 9 a.m. to 4 p.m., Monday through Friday 
  • Weekend work: planned for Sept. 9 - 10 and 16 - 17, 7 a.m. to 7 p.m.
  • Some lanes of Avondale will be temporarily closed for construction 
  • Expect delays throughout the Avondale corridor during construction