PSE Sammamish Juanita Transmission Line

Visit PSE's project webpage


PSE Project Map

What: Construct a new 115 kV transmission line from Sammamish Substation along the east side of Willows Road to the Juanita Substation in Kirkland.

Project Status: Approved
This project has been reviewed and approved by the City’s Hearing Examiner, a private, non-partisan land use attorney. 

Construction is anticipated to begin in the summer 2023.

Permit Application Review: The project included both a Site Plan Entitlement and Conditional Use Permit, which means this project has been through full project review and processed per the Redmond Zoning Code criteria. All permit requirements were met. 

Environmental Review: This project completed a full environmental review. The City of Kirkland was the lead agency working in partnership with the City of Redmond, per the State Environmental Policy Act (SEPA), which states that the city with the majority of the project takes the lead on environmental review. Environmental impacts disclosed were determined to be non-significant. 

The project exceeds the City’s 35% tree retention requirements, retaining 60% of the significant trees within the project area. All removed trees will be replaced per the City’s tree regulations

Minimal impacts to streams and wetlands will be mitigated per city regulations. PSE will replace six culverts, including three which are fish passable, in the project area.

Project Timeline:

  • 2008-2009: PSE began community outreach 
  • 2011-2012: PSE worked with Stakeholder Advisory Group (SAG) 
  • 2011-2012: PSE hosted community open houses in December 2011, June 2012, and August 2012 
  • Sept. 2012: SAG recommended preferred route 
  • 2014: PSE finds preferred and fallback route to have challenges
  • 2015 - 2019: PSE discussed locating in BNSF/RCC corridor east of Willows Road
  • March 2020: PSE filed land use applications, City issues notice of application (mailing within 500’, posted three yellow land use action signs, posted in City Hall and Redmond Library)
  • May 21, 2020: PSE hosted virtual neighborhood meeting (mailing within 500’ and parties of record)
  • Aug. 23, 2021: City issued notice of public hearing (mailing within 500’ and parties of record, posted three land use signs, posted in City Hall and Redmond Library and published hearing notice in Seattle Times)
  • Sept. 13, 2021: Hearing Examiner held public hearing
  • Sept. 29, 2021: Hearing Examiner issued approval decision, no appeals were filed
  • July 2022: City mailed a postcard to all Redmond residents and businesses with notification about the upcoming project
  • July 2023: PSE mailed a notice of construction letter to all property owners along the project alignment 
  • Summer 2023: Construction anticipated to begin


Project Number: LAND-2020-00198

Project Type:  Type III Conditional Use Permit and Type II Site Plan Entitlement

Notice
Notice of Application (PDF)

Public Hearing
September 13, 2021 at 6:00pm (PDF)
Hearing Examiner Schedule & Information for 2021 (LINK)