Project Updates

The Redmond Pool is currently in the first phase of essential improvements which include new mechanical and electrical systems, air handling units, boiler systems, roof and windows, and improved circulation. These improvements will result in better air and water quality, energy efficiencies and operational savings. Phase 2 includes locker room and lobby improvements, pool deck re-surfacing and ADA improvements.

Recently contractors discovered an existing but unknown condition. The substructure of the pool is compromised; there are areas where concrete has deteriorated leaving aggregate and rusting rebar behind. The damage extends sporadically from approximately 1’ to 5’ off the bottom of the pool’s deep end. This unexpected repair will take approximately 3 months to correct the substructure and complete the pool lining. To accommodate this unexpected delay the Redmond Pool will not open in November as previously scheduled and will remain closed to complete both Phase 1 and 2 and is expected to re-open in fall of 2020.


Redmond Pool Update - 10/24/19

While our contractor was demolishing the lining in the deep end of the pool, an existing but unknown condition was discovered. The substructure of the pool is compromised; there are areas where concrete has deteriorated leaving aggregate and rusting rebar behind. Anderson Poolworks investigated on Tuesday, 10/22/19 and found the damage extends sporadically from approximately 1’ to 5’ off of the bottom of the pool’s deep end.

The pool was scheduled to open in November after the first phase of work was completed but due to these new developments, we will calculate a new timeline for the pool when we have determined the scope of work for the structural engineers and Anderson Poolworks. We hope to have the new timeline available next week.

  1. Project Updates


Redmond Pool - September 2 work

September 3, 2019

The boilers were set up in their final location, and gas lines were reworked to the mechanical room. The domestic water lines over the pool were also replaced. Crews onsite continued to work on the air ducts, mechanical room, and the roof this week.


Redmond Pool- Concrete Pouring

August 26, 2019

Crews did demo work on the drywall throughout the facility, concrete pads were poured into the mechanical room for the equipment, and new boilers were placed. Work also continued on the roof, where details around the edges of the upper roof was completed.


Redmond Pool- New Boilers

August 12, 2019

Crews completed welding on the structural steel frame, completed ductwork and finalized the insulation taper and roofing on the upper roof.

Redmond Pool 8.12.19 _
Redmond Pool 8.12.19

August 5, 2019

Crews continued work on the upper roof – with the second half of the upper section completed this week. Work was also completed on installing and coating structural steel in the mechanical room, and testing was completed on the skylights.

8/6/19 Pool Update Status


8/6/19 Pool Update Status

July 29, 2019

This week the crews started the installation of the new taper system on the roof, and 40% of the upper food was installed with the new TPO surface membrane. A ramp was also constructed, and installed in the pool to allow crews to move lifts into the pool and completed work on the ACT ceiling above the pool.

7/29/19 Pool Work

July 22, 2019

Crews installed steel and structural steel components in the mechanical room, and removed filers out of the surge tank. Roof insulation was delivered, and staff continued to demo the upper roof.

7.22.19_Roof Work

7.22.19 Week Work

July 15, 2019

Crews continued to remove equipment from the mechanical room, including the concrete boiler flue, and are preparing to remove the concrete surge tank. Work also started on the roof of the Redmond Pool this week, with the removal of the existing roof above the mechanical room and the front lower roof.

Redmond Pool- Week 3

Redmond Pool- Week 4

July 8, 2019

All large pieces of equipment were removed from the mechanical room, and fencing was placed around the perimeter of the pool for safety and security. A carpenter team removed some of the ACT ceiling over the pool walkway to prepare for a clear space for new duct and lighting installation.

Redmond Pool- Week 3.1

July 1, 2019

Crews started the draining process of the Redmond Pool, and plumbers and fitters were onsite this week to demo the piping systems and pumps in the mechanical room. The next week will be focused on removing some of the largest systems, including the air handling units, and begin to scope and assess the pipes once the pool is fully drained

Redmond Pool- Drained completely

Jun 24, 2019- Redmond Pool Closed for Improvements

The Redmond Pool closed today to begin Phase 1 work of the Pool Improvement project. City crews and contractor staff started to drain the pool and prepare the space for improvement work to begin.

Redmond Pool draining

Redmond Pool Improvement Updates