1. Call for utility locates @ 1-800-424-5555.2. Submit a traffic control plan for review and approval with the
Right of Way Permit Application per Standard Specs pg. 2.3.
3. Applicant is required to send out "Construction
Notices" to residents 5 days prior to start of work.
4. Notify Construction Division at 425-556-2723
two (2) working days prior to the start of work. Provide street use
permit number, location, type of work, contractor name and telephone
number.
5. Existing utilities are required to be "potholed" prior
to construction. All open-cut street surfaces and hard surface areas
shall be backfilled with Controlled Density Fill (CDF) per Standard
Specs pg. 2.1 #3 & Standard Detail Drawing No. 201. Mixed designs
shall be submitted for review & approval.
6. All city utilities have priority. Reference placement vertically and
horizontally. Franchise utilities are required to be placed beneath
City water mains and services with 1' minimum vertical separation.
Horizontal separation requires a 5' minimum behind fire hydrants and
when paralleling City-owned utilities. There is a 10' minimum
requirement when adjacent to power vaults.
7. Requirement when encountering asbestos cement watermains: It is
required when intersecting these mains to remove and replace the
existing with Class 52 ductile iron for 10' on each side of the point
of intersection. Contractor is required to be asbestos certified.
8. Trench shoring is to meet minimum safety standards set by the
State of Washington Department of Labor and Industries. [Chapter
296-155 WAC.]
9. Requirements for type and placement of steel sheets: Minimum
size is 1" thick by 8' wide by 20' long with skid proof surface.
Sheets are to be pinned and cold mix placed on edges. Area is to be
kept clean at all times. "Steel plates ahead" warning signs
required.
10. Restoration of open-cut pavement sections shall meet the
requirements of Standard Specs Chapter 2 & Standard Detail Drawing
No. 201 & as directed by City Inspection.
11. When work area is at a signalized intersection, it is required
that the contractor coordinate construction activity with the City of
Redmond signal engineer at 425-556-2751 twenty-four (24) hours prior
to start of work. [See Standard
Specs pg. 2.4]
12. Silt and Erosion Control shall meet the requirements of the
RCDG 20E.90.10 code. Contractor is required to provide protection of
the City storm drain system. Concrete trucks are required to use a
designated washout area.
13. Restoration shall meet the requirement of Standard Spec Chapter
3. Roadway restoration shall include streets, sidewalks, driveways,
curb & gutter, traffic signs and markings, landscaping, and irrigation
systems (for Parks Dept systems contact Scott Van De Vanter @
425-556-2354). City of Redmond may require width or half-street grind
& overlay.
14. Final inspection and approval per Standard Specs. pg. 2.3 #15.
15. Record drawings per Standard Spec 1.2 #8.
16. Hours of work per Standard Spec 2.4 #4. Certain streets require
limited hours for construction.
17. Noise control per Standard Spec 1.2 #6 & Ordinance #2006.
18. Tree protection & replacement per Ordinance #1998.
19. Overtime hours will be billed to the applicant per Standard
Spec pg. 2.4 #4.
20. City of Redmond business licenses are required of all
contractors & subcontractors per Standard Spec pg. 1.1. Suppliers are exempt.
21. A copy of the
City of Redmond Standard Specifications
are
required to be on site at all times per Standard Spec pg 1.1 #3.