Location: On the bank of Lake
Sammamish near the 2400 block of West Lake Sammamish Parkway
Project Phase: In Planning
Estimated Timeline Schedule: Design
beginning spring 2010 / construction start is estimated to be summer 2010 /
completion estimated in fall 2010
Project Manager:
Phil Day,
425-556-2860
Project Description: The existing pump
station was built in the early 1970's and is need of extensive rehabilitation.
Minor maintenance work has been done to the station over its nearly 40-year
service life but the station is in poor condition and needs to be upgraded. It
serves approximately 24 lots in the Viewpoint neighborhood.
Updated: January 4, 2010

|