|

Location: Union Hill Road and 185th Ave NE
Current Project Activities: Preliminary
design and right of way acquisition
Project Phase: In Design
Proposed Timeline Schedule: Design began summer 2007;
construction start 2009
Project Manager:
Mike Paul,
425-556-2721
Project Description: This project will extend
185th Avenue NE to the north, through the UPS site, to Union Hill Road. A new
traffic signal will be constructed at the intersection of Union Hill Road and
185th Ave NE.
Updated: February 5, 2008

Location: East Lake Sammamish Parkway and NE
65th Street
Project Phase: Bidding completed, moving into the construction phase
Proposed Timeline Schedule: Construction start
April 2008; completion December 2008
Project Manager:
Steve Gibbs,
425-556-2729
Project Description: This project will widen
East Lake Sammamish Parkway through the intersection with NE 65 Street to tie
into the State improvements made to East Lake Sammamish Parkway and SR 202. The
City also plans to reconstruct the traffic signal, to place the existing
overhead utility lines underground, and provide new sidewalks and landscaping at
this intersection.
Updated: February 5, 2008

Location: East Lake Sammamish Parkway between
NE 65th St and 187th Ave NE
Current Project Activities: Pre-design work
Project Phase: In Design
Proposed Timeline Schedule: Design start February
2008; construction start summer 2008, completion
fall 2008.
Project Manager:
Mike Paul,
425-556-2721
Project Description: This project will remove
and replace damaged concrete panels, rehabilitate existing concrete pavement,
and resurface lanes and shoulders with asphalt pavement.
Updated: February 5, 2008

|