Location: NE 111th and 172nd Avenue NE
Current Project Activities: Permitting.
Project Phase: In Final Design
Proposed Timeline Schedule: Construction
summer 2010
Contact:
Dennis
Brunelle,
425-556-2724
Project Description: The
Abbey Road Pond is a large regional stormwater pond providing water quality and
detention for a large residential area, protecting a salmon-bearing stream. The
116th culvert replacement project in 2006 removed a fish barrier. Future
improvements to protect this stream are phased projects that will improve the
capacity, function, and maintenance access in the large Abbey Road Pond. The
first phase in 2010 will be construction of a new pond on City property adjacent
to the PSE powerline trail north of the Abbey Road Pond. The new pond will
provide additional flow control and water quality treatment for roads in the
area within an underutilized portion of City property.
Open House 12/3/09 - Flyer Information
Updated: November 23, 2009

Location: NE 116th Street between 169th
Court NE to 172nd Avenue NE
Current Project Activities: The project is
currently in the design phase.
Project Phase: In Design
Proposed Timeline Schedule: Design into 2010;
construction start late Spring 2010; completion Fall 2010
Contact:
Dennis
Brunelle, 425-556-2724
Project Description: The
goal of this project is to upgrade the existing profile of NE 116th Street
between 169th Avenue NE and 172nd Avenue NE to meet site distance and safety
standards along that portion of NE 116th Street at the apex of the hill fronting
the site of Fire Station #17.
Open House 12/3/09 - Flyer Information
Updated: November 23, 2009

Location: 16917 NE 116th St.
Current Project Activities: The project is
currently in the design phase.
Project Phase: In Design
Proposed Timeline Schedule: Design into 2010;
demolition of existing buildings February 2010; construction start 2010; completion 2011
Contact: Construction Division, 425-556-2723
Project Description: The
City is in the design phase for the new Fire Station No. 17 located in
the rapidly developing North Redmond neighborhood. The new station will house
fire and aid staff. Informational open houses were held on June 25, 2009,
and December 3, 2009,
to discuss design considerations. Demolition of the existing on-site buildings
will occur in February 2010.
Open House 12/3/09 - Flyer Information
Newsletter: June 2009
Newsletter: April 2009
Newsletter: March 2010
Updated: March 15, 2010

Location: NE 124th and SR 202
Current Project Activities: Securing required
right-of-way and final permits
Project Phase: Final Design
Proposed Timeline Schedule: Construction
summer 2010; completion early 2011
Project Manager:
Steve Gibbs,
425-556-2729
Project Description: Improvements to this
intersection will add two additional thru lanes to the east leg of the
intersection and the left-turn lane for westbound NE 124th Street to southbound
SR 202 will also be lengthened to provide more storage and reduce the backups.
Curb, gutter, planter strip and sidewalk and bike lanes will be placed along the
eastern leg. A second left-turn lane will also be added on the south leg of SR
202 to westbound NE 124th Street. Traffic signal modifications will be
made to accommodate the revised channelization.
Open House 12/3/09 - Flyer Information
Updated: March 15, 2010

Location: West of Redmond-Woodinville
Road along the south edge of Valley Estates and into the Mondavio plat
(approximately NE 107th) to the Sammamish River
Current Project Activities: Working on
designing and permitting
Project Phase: In Design
Proposed Timeline Schedule: Start design
stream enhancements and culvert fall 2009; start construction for
the high flow bypass and construction for stream enhancements and culvert summer 2010.
Additional Project Information
Project Manager:
Mike Haley,
425-556-2843
Project Description: Enhancements to the
stream that runs from the Redmond-Woodinville Road to the Sammamish River along
the south edge of Valley Estates and into the Mondavio plat.
Open House 12/3/09 - Flyer Information