|

View Project updates and video

View Project updates and video
or View
background information

View Project updates and video

View Project updates and video

2010 Sidewalk Improvement Projects
Locations: North side of NE 79th Street
from 168th Avenue NE to 170th Avenue NE near Anderson Park /
South side of NE 90th Street from Willows Road to 154th
Avenue NE
Project Phase: Easement acquisition and final design
Estimated Timeline Schedule: Construction
is estimated to start in April 2010 / estimated completion in
August 2010
Project Manager:
Phil Day,
425-556-2860
Project Description: This project is this
year's portion of the City's ongoing sidewalk program to improve pedestrian
safety and fill in missing link sidewalk segments. It will also upgrade the
storm sewer on NE 79th in advance of the upcoming pavement overlay project, and
complete the underground conversion of overhead utilities in this area.
Updated: January 4, 2010

2009 Sidewalk Improvement Projects
Locations: South side of Redmond
Way from Willows Road to 160th Court / PSE Trail to Rose Hill
/ NE 40th Street
Project Phase: In Construction
Estimated Timeline Schedule: Construction
is estimated to start in November 2009 / estimated completion in
March 2010
Project Manager:
Phil Day,
425-556-2860
Project Description: Approximately 700 linear
feet of curb, gutter and a five-foot concrete sidewalk will be installed on the
south side of Redmond Way from Willows Road to 160th Court..
Updated: December 7, 2009

Location: 161st Avenue NE Extension
from Bear Creek Parkway to Redmond Way
Project Phase: In Design
Estimated Timeline Schedule: Design
beginning August 2009 / construction
start is estimated to be summer 2010 / completion estimated in fall 2011
Project Manager:
Lisa
Singer,
425-556-2726
Project Description: Design and construction
of 161st Avenue NE that will connect the new Bear Creek Parkway north to
downtown at Redmond Way. Project features will include a new street connection,
signal improvements, sidewalks, street lighting, utilities and landscaping. .
Updated: August 11, 2009

Location: Various.
Current Project Activities: Preliminary
design and permitting
Project Phase: In Design
Estimated Timeline Schedule: Construction
expected to start Spring 2010
Project Manager:
Mike Haley,
425-556-2843
Project Description: Redmond Way Stormwater
Trunk will convey all stormwater runoff directly from the east end of downtown
Redmond to the Sammamish River. The Redmond Way Stormwater Quality Facility will
collect low flows from the stormwater trunk and provide water quality treatment
to the runoff prior to discharge to the River.
Project Information Sheet
Updated: August 24, 2009

|