The following projects are being managed by outside agencies, such as
King County or the Washington State Department of Transportation (WSDOT),
but are planned or currently under construction inside the city limits
of Redmond.
Novelty Hill Road Widening
King County Project Manager: Mike O'Neil (206-263-3538)
City of Redmond Project Manager: Jeanne Justice
(jjustice@redmond.gov)
City of Redmond funding contribution:
$150,000
Status: Currently in environmental impact study.
Description: This project will mitigate traffic for Redmond Ridge East,
the 800 homes coming in on Novelty Hill. The intersection is a bottleneck,
but the congestion is on westbound NE 124 Street and southbound
Redmond-Woodinville Road during the morning and eastbound on NE 124 Street
during the evening commute.
For more information, go to
www.metrokc.gov/kcdot/roads/cip. In the Quick Search box, type
Novelty. It is project #100992.
This page was last reviewed on July 12, 2007..
|