Tosh Creek 156th Avenue NE Flow Splitter

Vicinity Map

Location: 156th Avenue NE near NE 51st Street

Project Phase: Construction

Estimated Timeline Construction expected to begin in June 2017 and last for approximately two months

Contact: Eric Dawson, 425-556-2867

Project Last Updated: 05/22/2016

Description:
The existing flow splitter directs stormwater flows from 156th Ave NE. Approximately 15% of the flows drain to Tosh Creek with the remainder flowing down the NE 51st Street trunk, which discharges into the wetlands near West Lake Sammamish Parkway. The project will make minor modifications to the flow splitter to optimize its control of flows, reducing high flows to Tosh Creek while maintaining the base flows necessary for stream health.

Project Data:
156th Flow Splitter Plans

Tosh Creek Restoration

For more information on the full restoration plan visit these pages.

Project Contact

Project Manager
Eric Dawson
425-556-2867