Education Water System Zone Improvements

Vicinity Map

Location:  Education Hill

Project Phase: Construction

Estimated Timeline: Construction began February 21, 2017, and is expected to be substantially complete by the end of September 2017, two months ahead of schedule.

Contact: Dennis Brunelle, 425-556-2724

Page Last Updated: 09/13/17

Paving status: Grinding and paving operations on NE 92nd St., 170 Ave. NE, 171st Ave. NE, 172nd Ave. NE and NE 88th St. will begin Thursday, September 14, and continue until September 22, weather permitting.

Description:
The City of Redmond’s Education Hill Water System Improvements project is a water system project that will construct approximately 5,700 feet of new water line. These improvements will increase water pressure and provide greater fire flows in the high elevation area south of the Education Hill Reservoirs located adjacent to NE 104th Street.

These water pipeline improvements will occur along:
  • 171st Avenue NE from NE 95th Street to NE 88th Street
  • NE 92nd Street from 169th Court NE to Nike Park (waterline installation complete)
  • NE 88th Street from 171st Avenue NE to 172nd Avenue NE
  • 172nd Avenue NE from NE 92nd Street to NE 88th Street
  • 170th Avenue NE from NE 92nd Street to end of cul-de-sac (waterline installation complete)
Traffic moving through these areas may encounter delays due to construction activity within the roadways. Residents are advised to use alternate routes whenever possible.

Picture of new waterline installation in 171st Ave NE
Installation of new waterline in 171st Ave. NE